Fort to Fort power line upgrade completed on time despite challenges

NO F40 FFE-FFW

Want to read more?

At the start of the pandemic in March we took the decision to make online access to our news free of charge by taking down our paywall. At a time where accurate information about Covid-19 was vital to our community, this was the right decision – even though it meant a drop in our income. In order to help safeguard the future of our journalism, the time has now come to reinstate our paywall, However, rest assured that access to all Covid related news will still remain free.

To access all other news will require a subscription, as it did pre-pandemic. The good news is that for the whole of December we will be running a special discounted offer to get 3 months access for the price of one month. Thank you for supporting us during this incredibly challenging time.

We value our content and access to our full site is only available with a  subscription. Your subscription entitles you to 7-day-a-week access to our website, plus a full digital copy of that week’s paper to read on your pc/mac or mobile device.  In addition, your subscription includes access to digital archive copies from 2006 onwards.

Just want to read one issue? No problem you can subscribe for just one week (or longer if you wish).

Already a subscriber?

 

Subscribe Now

SSEN Transmission and its principle contractor Balfour Beatty have successfully completed, on time, the challenging upgrade of the existing Fort Augustus to Fort William overhead electricity line.

Bringing to a close two years of hard work, the project team has upgraded one of the north of Scotland’s longest serving power lines and by doubling its capacity, provided additional capacity to accommodate the growth in renewable electricity in the area, supporting the transition to net zero emissions.

The 44km line was originally built in the 1950s following the passing of the Hydro Act, which revolutionised and industrialised the north of Scotland by bring power to the glens.

After nearly 70 years’ service, the project team needed to determine the best way to upgrade the line while minimising the impact to the local communities surrounding it.

The location of the line, which crosses public roads, railway lines and the Caledonian Canal, following steep terrain throughout its route, added to the challenges that the team would need to be creative to overcome.

Looking at the towers, they reviewed if the current towers were in a good enough condition to be retained. This would remove the need for a new line to be built and a new route for the line found, decreasing the level of construction impact on the local community.

Innovation was the key, with the existing conductor changed to an ACCC conductor which is made using special aluminium wrapped around a carbon composite core; the change means the conductor will be twice as strong as the steel, 70 per cent lighter and able to carry twice the amount of power.

By using this technology and strengthening the existing towers only five of the 156 towers needed to be replaced.

A very detailed and extensive Emergency Return to Service plan was put in place to restore supplies to customers in the event of a fault occurring on the network while this work was in progress.

The steep sides of the glen the line runs through made access difficult and would mean new access tracks would have to be built to complete the works. In some locations the side slopes were so steep specially built sets of stairs were installed to allow access up the hillside to the towers, then once the work was complete moved on to the next section.

Where the line crossed the A82, local roads and the canal, netting was placed under the wires on scaffolding to protect the areas below. Where scaffolding could not be used, another innovation was the use of Catenary Support System (CSS) over the Caledonian Canal and A82 and A87 – this is where a motorised tug pulls the new conductor and rollers along the old conductor between towers.

This was a great success as it meant that no road closures or closure of the canal was required, keeping the local community, tourists and road users moving.

Lead project manager Pat Howe said he was immensely proud with what had been achieved: ‘At the outset of the project we couldn’t have imagined we would have been able to retain so much of the existing infrastructure as well as doubling the capacity of the line.

‘Our first priority is always to safely deliver a robust, efficient and reliable network to our customers in the most sustainable way. In delivering this essential service, we have demonstrated that this is achievable, even on a project that contained as many challenges as this one.

‘Our team has worked closely with the local community throughout the project, being awarded an Excellent in the Considerate Constructors Scheme, raising over £8000 for local charities, including the Scottish Air Ambulance, Lochaber Hope and the Highland Hospice.’