Landslip closes rail line at Lochailort until July 13

NO F27 rail landslip 01
NO F27 rail landslip 01

Want to read more?

We value our content  and access to our full site is  only available with a  subscription. Your subscription entitles you to 7-day-a-week access to our website, plus a full digital copy of that week’s paper to read on your pc/mac or mobile device In addition your subscription includes access to digital archive copies from 2006 onwards

Just want to read one issue? No problem you can subscribe for just one week (or longer if you wish)

Already a subscriber?

 

Subscribe Now

Network Rail engineers are working around-the-clock to repair flood damage at Lochailort on the West Highland Line after a landslip last week.

The line will remain closed between Fort William and Mallaig until Monday July 13, while engineers work to rebuild more than 80m of railway washed away by the severe weather.

More than 1,600 tons of material has been displaced and engineers will have to completely rebuild the supporting embankment, ballast and track before the line can reopen.

Liam Sumpter, Network Rail Scotland route director, said: ‘Our engineers are working hard to fully assess the damage and complete the repairs needed to reopen the line as quickly as possible for customers.

‘Flash flooding has caused significant damage at several points along an 80m stretch of track and we will need to rebuild the track-bed and supporting embankments before we can reopen the line.

‘We are working as quickly as possible to complete these repairs in what is a very challenging location.’

NO F27 rail landslip 02

 

NO F27 rail landslip 03